Client Armstrong Solicitors

Client: Armstrong Solicitors
Contractor: Chapel Green Contracts Ltd.
Contract Value: £572,000
Status: Twelve Months Defects

BL is a gentleman and was injured in a road traffic accident. This has left him paraplegic, wheelchair dependent with little use of his left hand and arm. There were no suitable bungalows with land in his immediate village locality so a small bungalow on a large plot was purchased and demolished and a new purpose-built property designed and built.

The scheme comprised the demolition of existing dormer bungalow and construction of new two storey property to include bedroom, specialist bathroom and therapy space with hoisting, glass through lift and facilities for overnight carers. Works were taken through Planning and Building Regulations approvals, tender and on site to completion.